SL. No. | Schemes/ Services offered by the Department/Section | Major Achievement for the F.Y: 2021- 22 & 2022-23(Schemes/ Services ) | Remarks |
---|---|---|---|
1 | High Drain | Construction of High Drain with slab from Jaigaon Super Market to Gopimohan (Phase-III) Jaigaon in the District of Alipurduar | Completed |
2 | Approach Road | Construction of Approach Road for the SWM Project at Jaigaon in the District of Alipurduar | Completed |
3 | Hume Pipe Culvert | Construction of Hume Pipe Culvert (No-1) at the Approach road of the SWM Project at Jaigaon in the District of Alipurduar | Completed |
4 | High Drain with slab | Construction of High Drain with slab from Jaigaon Super Market to Gopimohan (Phase-II) Jaigaon in the District of Alipurduar | Completed |
5 | High Drain with slab | Construction of High Drain with slab from Sani Maya Lama house Via Muri Factory side up to Dil Bahadur House (Phase-1) Jaigaon in the District of Alipurduar | Completed |
6 | High Drain with slab | Construction of High Drain with slab from Sani Maya Lama house Via Muri Factory side up to Dil Bahadur House (Phase-2) Jaigaon in the District of Alipurduar | Completed |
7 | High Drain with slab | Construction of High Drain with slab from Sani Maya Lama house Via Muri Factory side up to Dil Bahadur House (Phase-3) Jaigaon in the District of Alipurduar | Completed |
8 | Black top road | Construction of Black top road near Dalsingpara Gram Panchayet Office at Dalsingpara in the District of Alipurduar | Physical progress- 60%. The work will be completed by February, 2023. |
9 | Roll Steel Bridge | Construction of Roll Steel Bridge at Jaigaon near Gopimohan in the District of Alipurduar | Physical progress- 80%. The work will be completed by January, 2023. |
10 | Hume Pipe Culvert | Construction of Hume Pipe Culvert (No-2) at the Approach road of the SWM Project at Jaigaon in the District of Alipurduar | The work was washed away during last monsoon |
11 | Bituminous Road | Construction of Bituminous Road near Nala Sarak & Jogikhola River at Jaigaon in the District of Alipurduar | Completed |
12 |
Bituminous Road
|
Construction of Bituminous Road from Lama Chowpathy to Masjid Bridge at Guabari, Jaigaon in the District of Alipurduar |
Completed |
13 |
Bituminous Road and One side drain
|
Construction of Bituminous Road and One side drain from Sunil Karmakar house to K.B. Karhi house at Jaigaon in the District of Alipurduar |
Completed |
14 |
Bituminous Road
|
Construction of Bituminous Road from Jaigaon Post office to Buddhist Gumpha via WBSEDCL Office at Jaigaon in the District of Alipurduar |
Completed |
15 |
Bituminous Road and two side drains
|
Construction of Bituminous Road and two side drains from Kisan Rai to Horimaya Pradhan house (via Surjaman Lama’s house) at Jaigaon in the District of Alipurduar |
Completed |
16 |
Bituminous Road with one side drain
|
Construction of Bituminous Road with one side drain from Nijam house via ICDS Center to Binod Mothey house at Jaigaon in the District of Alipurduar |
Completed |
17 |
High Drain with slab |
Construction of High Drain with slab from Jaigaon Hindi Jr. School to Ajib Mia House at Guabari, Jaigaon in the District of Alipurduar
|
Completed |
18 |
High Drain with slab |
Construction of High Drain with slab from Bakkar Mia to Ahmed Mia house at Guabari, Jaigaon in the District of Alipurduar |
Physical progress- 75%. The work will be completed by January, 2023. |
19 |
C.C. Road with drain |
Construction of C.C. Road with drain from Dewan house to Ranjit Biswakarma house via St. Pal Church, Hatkhola, Jaigaon, in the District of Alipurduar |
Physical progress- 75%. The work will be completed by January, 2023. |
20 |
C.C. Road with drain |
Construction of C.C. Road with drain from Siv mandir to Kajiman Bhujel house at Dalsingpara in the District of Alipurduar. |
Physical progress- 80%. The work will be completed by January, 2023. |
21 |
C.C. Road with repairing of existing drain |
Construction of C.C. Road with repairing of existing drain from Satpal Maharaj Ahram to Suresh Chowdhuri house at Jaigaon at Jaigaon, in the District of Alipurduar. |
Completed |
22 |
C.C. Road with drain |
Construction of C.C. Road with drain from Kajma Bhujel house to Dalsingpara main road at Chhetri Line, Dalsingpara near Gopimohan in the District of Alipurduar |
Physical progress- 75%. The work will be completed by January, 2023. |
23 |
Road with drain |
Construction of Road with drain from Jaigaon PHC to Fire station via Jaigaon College, Jaigaon in the District of Alipurduar. |
Completed |
24 |
C.C. Road with drain |
Construction of C.C. Road with drain from Guru Gyan Academy via Raj kumar Rai house, Naya Line to Kishore Manger house, Dalsingpara in the District of Alipurduar. |
Physical progress- 75%. The work will be completed by January, 2023. |
25 |
C.C. Road with drain |
Construction of C.C. Road with drain from Uttam Sharma house to Bhojraj Chhetri house, Digbir Line, Dalsingpara in the District of Alipurduar. |
Physical progress- 75%. The work will be completed by January, 2023. |
26 |
C.C. Road with drain |
Construction of C.C. Road with drain from Guru Gyan Academy to Shiv Mandir, Digbir Line, Dalsingpara in the District of Alipurduar. |
Physical progress- 75%. The work will be completed by January, 2023. |
27 |
C.C. Road with drain |
Construction of C.C. Road with drain from John Shop to PMGSY Road with its branch road at T.G. Line No.03, Jaigaon in the District of Alipurduar. |
Completed |
28 |
Road |
Construction of Road from Bikram Gurung house to Ajay Kami House at Indrani Toll-2, Khokla busty, Jaigaon in the District of Alipurduar. |
Physical progress- 75%. The work will be completed by January, 2023. |
Jaigaon Development Authority(U.D. & M.A. Department)
Email Id:- jdaoffice[dot]jaigaon[at]gmail[dot]com
Address:- Jaigaon, Alipurduar